SBI PO Time and Work Mostly Asked Questions, Download Free PDF
Sign Up on PracticeMock for Free Test, General Awareness, Current Affairs, Exam Notifications and Updates

Home » SBI PO » SBI PO Time and Work Mostly Asked Questions

SBI PO Time and Work Mostly Asked Questions are among the most important topics for candidates aiming to score well in the Quantitative Aptitude section. This chapter regularly appears in SBI PO examinations and is known for testing a candidate’s understanding of efficiency, work distribution, and time management concepts. Many aspirants find Time and Work challenging because of its diverse question patterns, but with the right practice, it can become a highly scoring area. In this article, you will find SBI PO Time and Work Mostly Asked Questions, a practice quiz, a free PDF download, and answers to frequently asked questions to strengthen your preparation.

Attempt SBI PO Time and Work Mostly Asked Questions Quiz

Regular practice is essential to master Time and Work questions for the SBI PO exam. Attempt the SBI PO Time and Work Mostly Asked Questions Quiz below to assess your understanding of work efficiency, combined work, wages, and work completion concepts. Solving these questions will help you improve your calculation speed and accuracy while preparing for the examination.

Time and Work Section Score: 0.00

Q1. A can complete a work in 25 days and B can do the same work in 20 days. They started working together, but A leaves after 5 days. How many total days did B work?

Explanation: Let total work = LCM(25, 20) = 100 units.
Efficiency of A = 100/25 = 4 units/day. Efficiency of B = 100/20 = 5 units/day.
Together they do (4+5) = 9 units/day. In 5 days, they complete 9 x 5 = 45 units.
Remaining work = 100 – 45 = 55 units.
B does the remaining work alone in 55 / 5 = 11 days.
Total days B worked = 5 (with A) + 11 (alone) = 16 days.

Q2. 15 men can complete a project in 20 days. In how many days can 20 men complete the same project?

Explanation: Use the formula M1 x D1 = M2 x D2 (where M = Men, D = Days).
15 x 20 = 20 x D2
300 = 20 x D2
D2 = 300 / 20 = 15 days.

Q3. A is 40 percent more efficient than B. If B takes 21 days to complete a work, how many days will A take to do the same work?

Explanation: Efficiency Ratio of A:B = 140:100 = 7:5.
Time taken is inversely proportional to efficiency. So Time Ratio of A:B = 5:7.
If B takes 7 parts = 21 days (so 1 part = 3 days).
A will take 5 parts = 5 x 3 = 15 days.

Q4. A can do a work in 10 days and B can do it in 15 days. They work on alternate days starting with A. In how many days will the work be completed?

Explanation: Total work = LCM(10, 15) = 30 units.
Efficiency of A = 3, Efficiency of B = 2.
They work alternately: Day 1 (A does 3), Day 2 (B does 2).
In a 2-day cycle, work done = 5 units.
To complete 30 units, they need 30/5 = 6 cycles.
Total days = 6 cycles x 2 days/cycle = 12 days.

Q5. A and B together can complete a work in 8 days. If B alone can complete the work in 12 days, in how many days can A alone complete it?

Explanation: Total work = LCM(8, 12) = 24 units.
Efficiency of (A+B) = 24/8 = 3 units/day.
Efficiency of B = 24/12 = 2 units/day.
Efficiency of A = (A+B) – B = 3 – 2 = 1 unit/day.
Time for A alone = Total Work / A’s efficiency = 24 / 1 = 24 days.

Q6. A takes twice as much time as B and thrice as much time as C to complete a piece of work. Working together, they can finish it in 2 days. In how many days can B alone complete the work?

Explanation: Let A’s time be 6x days. Then B’s time = 3x days, and C’s time = 2x days.
Efficiency is inverse to time. Efficiency ratio A:B:C = 1/6x : 1/3x : 1/2x = 1 : 2 : 3.
Total efficiency = 1 + 2 + 3 = 6 units/day.
They finish in 2 days, so Total Work = 6 x 2 = 12 units.
B’s efficiency is 2 units/day. Time for B = 12 / 2 = 6 days.

Q7. A, B, and C can complete a work in 10, 20, and 30 days respectively. If they all work together, how many days will they take?

Explanation: Total work = LCM(10, 20, 30) = 60 units.
Efficiencies: A = 6, B = 3, C = 2.
Total efficiency (A+B+C) = 6 + 3 + 2 = 11 units/day.
Time taken together = 60 / 11 = 5.45 days.

Q8. 5 men finish a piece of work in 6 days while 10 women finish it in 5 days. In how many days can 5 women and 3 men together finish the same work?

Explanation: 5 Men x 6 days = 30 Man-days. (1 Man takes 30 days).
10 Women x 5 days = 50 Woman-days. (1 Woman takes 50 days).
Total Work = LCM(30, 50) = 150 units.
Efficiency of 1 Man = 5. Efficiency of 1 Woman = 3.
Efficiency of (5 Women + 3 Men) = (5 x 3) + (3 x 5) = 15 + 15 = 30 units/day.
Time taken = 150 / 30 = 5 days.

Q9. A completes half of a piece of work in 5 days. B completes one-third of the same work in 5 days. If they work together, in how many days will the work be completed?

Explanation: If A does 1/2 work in 5 days, A can do full work in 10 days.
If B does 1/3 work in 5 days, B can do full work in 15 days.
Total work = LCM(10, 15) = 30 units.
Efficiency of A = 3, Efficiency of B = 2. Together = 5 units/day.
Time taken together = 30 / 5 = 6 days.

Q10. A takes 30 days to finish a task and B takes 40 days to finish it. They work together for 12 days, then A leaves. In how many days will B finish the remaining work?

Explanation: Total work = LCM(30, 40) = 120 units.
Efficiency of A = 4, Efficiency of B = 3.
Together their efficiency = 7 units/day.
Work done in 12 days = 12 x 7 = 84 units.
Remaining work = 120 – 84 = 36 units.
B finishes remaining work alone in 36 / 3 = 12 days.

Quiz Summary

Attempted
0
Correct
0
Wrong
0
Unattempted
0
Final Score: 0.00

Download SBI PO Time and Work Mostly Asked Questions PDF

Candidates who want a comprehensive collection of practice questions can download the SBI PO Time and Work Mostly Asked Questions PDF from the link below. The PDF includes important exam-level questions, detailed solutions, and shortcut techniques that can help you solve Time and Work problems more efficiently. Regular revision through this PDF can significantly improve your confidence before the SBI PO examination.

SBI PO Exam PatternSBI PO Previous Year Question Paper
SBI PO NotificationBudget 2026 Banking Exam Strategy
Puzzle Solving Tricks Used by Toppers at Mains LevelTop 50 Banking Awareness Q&A for 2026
SBI PO Eligibility Criteria SBI PO Salary
SBI PO VacanciesSBI PO Syllabus

FAQs on SBI PO Time and Work Mostly Asked Questions

What are SBI PO Time and Work Mostly Asked Questions?

SBI PO Time and Work Mostly Asked Questions are the commonly asked Time and Work problems that frequently appear in SBI PO and other banking examinations. These questions evaluate a candidate’s ability to calculate work efficiency, completion time, and combined work scenarios.

Why is Time and Work important for SBI PO preparation?

Time and Work is considered an important scoring topic because questions are usually formula-based and can be solved quickly with sufficient practice. A strong command of this chapter can help candidates maximize their marks in the Quantitative Aptitude section.

Which concepts should I focus on in SBI PO Time and Work?

Candidates should focus on work efficiency, individual and combined work, pipes and cisterns, wages, work fractions, and alternate work scenarios. Understanding these concepts will help in solving most SBI PO Time and Work Mostly Asked Questions.

Where can I download the SBI PO Time and Work Mostly Asked Questions PDF?

You can download the SBI PO Time and Work Mostly Asked Questions PDF from the section above. It contains carefully selected questions, detailed explanations, and revision material designed specifically for banking exam aspirants.

How can I improve my performance in SBI PO Time and Work questions?

To improve your performance, practice a variety of Time and Work questions daily, learn shortcut methods, revise formulas regularly, and attempt mock tests. Consistent practice of SBI PO Time and Work Mostly Asked Questions will help you solve questions faster and with greater accuracy during the exam.

    Free Mock Tests for the Upcoming Exams

Disclaimer: PracticeMock articles — exam analysis, expected cut‑offs, expected topics, exam pattern, syllabus, strategies, dates, results, recruitment updates — are for guidance only. Exams are conducted by SSC, IBPS, SBI, RBI, SEBI, NABARD, UPSC, IRDAI, PFRDA, and other authorities. Always check the official notifications/websites for verified information. PracticeMock content is not official.

By Abhishek Jatariya

Hello Guys, I am Abhishek Jatariya (B.Tech (IT), HBTU Kanpur). At PracticeMock I am a dedicated Government Job aspirant turned passionate Content writer & Content creator. My blogs are a one-stop destination for accurate and comprehensive information on exams like SSC, Railways, and Other PSU Jobs. I am on a mission to provide you with all the details about these exams you need, conveniently in one place. I hope you will like my writing.

Leave a Reply

Your email address will not be published. Required fields are marked *

Sign up to Download PDF