Time and Work is an important topic in the Quantitative Aptitude section of the IBPS PO exam. It involves calculating the time taken by individuals or groups to complete a certain task, based on their efficiency. Questions are framed on real-life situations like workers completing jobs, filling tanks, or emptying pipe tanks. A strong understanding of this topic helps you solve related problems quickly during the exam. In this blog, we will tell you the full concept that you can solve the time and work questions.

 

Role of Time and Work Questions in Prelims

In the IBPS PO Prelims, Time and Work questions are generally simple and formula-based. They typically involve direct calculations where you need to find the time taken by two or more people to finish a task or vice versa. The most common methods used in these questions are the one-day work method and the LCM method to find efficiency. There are usually no complex conditions in prelim-level questions, making them scoreable if you know the basics. Candidates should focus on speed and accuracy since these questions carry equal marks and can be solved quickly compared to other arithmetic topics.

Best Study Resource for IBPS PO 2025 Exam

Here we are providing the Quant, Reasoning, and English mock test series. It contains free full-length mock test, Topic tests, Mini Mock Tests, and sectional Mock Tests.

  1. Quantitative Aptitude Test Series:
IBPS PO Quant Tests Series 
Quant Topic TestsAttempt Now 
Quant Mini mock TestsAttempt Now 
Quant Sectional Mock TestsAttempt Now 
A Free Full-length Mock TestAttempt Now 

2. Reasoning Test Series:

IBPS PO Reasoning Tests Series 
Reasoning Topic TestsAttempt Now 
Reasoning Mini mock TestsAttempt Now 
Reasoning Sectional Mock TestsAttempt Now 
A Free Full-length Mock TestAttempt Now 

3. English Test Series:

IBPS PO English Tests Series 
English Topic TestsAttempt Now 
English Mini mock TestsAttempt Now 
English Sectional Mock TestsAttempt Now 
A Free Full-length Mock TestAttempt Now 

Key Concepts Of Time and Work 

1. One-Day Work Method

If A completes the work in 10 days:

  • A’s 1-day work = 1/10.

If B completes the same work in 15 days:

  • B’s 1-day work = 1/15.

If A and B work together:

  • Combined 1-day work = 1/10+1/15= 1/6
  • So, they finish the work in 6 days.

2. LCM Method for Easy Calculation

Instead of fractions, assume the total work as the LCM of the given days.
Example:

  • A = 10 days, B = 15 days → LCM = 30 units.
  • A’s efficiency = 30/10=330/10 = 330/10=3 units/day.
  • B’s efficiency = 30/15=230/15 = 230/15=2 units/day.
  • Together = 5 units/day → Time = 30 ÷ 5 = 6 days.

4. Alternate Day Work

If A and B work on alternate days:

  • First, calculate two-day work = A’s 1-day work + B’s 1-day work.
  • Divide the total work by the combined two-day work to find the number of full cycles.
  • Then calculate the remaining work.

5. Pipes and Cisterns

  • Filling = Positive work, Emptying = Negative work.
    Example:
    A pipe fills in 12 hrs, another in 15 hrs, and an outlet empties in 10 hrs

6. Partial Work

If workers start together but one leaves after a few days:

  • Calculate work done by both first, subtract from the total, and then find the remaining work done by the other.

7. Work and Wages

  • Wages are directly proportional to work done.
  • If A and B share work in a ratio of 2:3, wages will also be divided in a 2:3.
banking Plus Course

Top 10 Tips to Solve Time and Work Questions Effectively

 1.  Clear Your Basics First

Before jumping into tricky problems, make sure you clearly understand the relationship between time, work, and efficiency. Remember the simple rule: More efficiency = Less time, and vice versa.

 2. Focus on the One-Day Work Concept

This is the backbone of Time and Work problems. If a person finishes work in 12 days, their 1-day work is 1/12. Start every problem by finding this first.

 3. Use Smart Shortcuts for Combined Work

When two or more people work together, add their 1-day work. Example: A = 1/10, B = 1/15, together = 1/10 + 1/15 = 1/6. Avoid long steps by using fractions smartly.

 4. Master the LCM Technique

Instead of working with fractions, assume the total work as LCM of the given days. This makes the calculation faster and helps in ratio-based problems.

 5. Break Down Complex Problems

For lengthy problems like “A works for 3 days, then B joins,” split the work into parts. Calculate what A did first, then how much is left, then assign it to B.

 6. Visualize with Diagrams for Pipes and Cisterns

Treat each pipe as a worker. Filling pipes are positive, emptying pipes are negative. Visualizing this helps in solving these problems easily without confusion.

 7. Watch for Alternate Day Traps

If A and B work on alternate days, calculate a 2-day combined work cycle first. Then check if any extra day is needed for the leftover work.

 8. Learn Efficiency and Ratio Tricks

If A is 50% more efficient than B, then A’s efficiency is in the ratio 3:2. This avoids extra calculations and saves time in exam conditions.

9. Memorize Standard Percentage Changes

In mains-level questions, sometimes workers become 20% less efficient or 25% more efficient. Learn to quickly apply percentage change to their time taken.

10. Practice, Practice, Practice

The best way to master Time and Work is by solving at least 40-50 questions of different types—basic, mixed, and main-level tricky problems. Regular practice improves speed and accuracy.

Conclusion

Time and Work is a scoring topic if your basics are clear. Always start by finding one-day work and then calculate the required time or efficiency. Using LCM helps simplify calculations for multiple workers. For mains-level problems, be prepared for tricky combinations and ratio-based questions. Regular practice and understanding the logic will help you attempt these questions quickly and accurately in the IBPS PO exam.

Click the link below to join our exclusive Telegram group for expert guidance, real-time doubt clearing, and personalized tips to boost your banking exam prep.

Also Read:

IBPS PO Exam PatternIBPS PO Salary
IBPS PO SyllabusIBPS PO Cut Off

FAQs

Q1. Is Time and Work important for IBPS PO?

Yes, it is frequently asked in both Prelims and Mains.

Q2. What is the basic formula?

 Work = Rate × Time or Time = Work ÷ Rate.

Q3. How to solve alternate-day problems?

Calculate the work done in two days, then divide the total work.

Q4. Are pipes and cistern questions part of Time and Work?

 Yes, they are an application of the same concept.

    Free Mock Tests for the Upcoming Exams

Disclaimer: PracticeMock articles — exam analysis, expected cut‑offs, expected topics, exam pattern, syllabus, strategies, dates, results, recruitment updates — are for guidance only. Exams are conducted by SSC, IBPS, SBI, RBI, SEBI, NABARD, UPSC, IRDAI, PFRDA, and other authorities. Always check the official notifications/websites for verified information. PracticeMock content is not official.

By Akansha Garg

Hi, I’m Akansha, a post-graduate in Economics with a passion for helping banking aspirants succeed. Having personally cleared multiple banking exams, both Prelims and Mains. I understand what it takes to crack them. Through my blog, I share updated exam information, smart strategies, and practical tips to help you prepare better and achieve your goals.

Leave a Reply

Your email address will not be published. Required fields are marked *